P896 Site visit for House project at Shamgarh, Mandsaur Madhya Pradesh for Mr. Gaurav Chandrawat

Project Name: Classic House

Project Location: Shamgarh, Mandsaur, Madhya Pradesh
Client: Mr. Gaurav Chandrawat
Date of Visit: 19th August 2025
Visited By:

  • Dr. Chandra Shekhar Changeriya (Architect, Indian Architect Team)

  • Er. Arjun Janva (Engineer, Indian Architect Team)


1. Purpose of Visit

The site visit was conducted to inspect the ongoing construction progress, verify structural formwork and layout alignments, and address execution-related queries with the site team.


2. Observations & Inspections

a. Structural Inspection:

  • The staircase formwork was checked in detail. Proper alignment and support through shuttering were confirmed.

  • Formwork for beam and slab elements was in place with adequate vertical supports using wooden props.

  • Placement of bricks and support systems were visually inspected for stability and load-bearing safety.

b. Measurement & Layout:

  • Foundation levels and column grid points were measured and verified using a measuring tape.

  • Adjustments were suggested in a few areas where layout deviations were observed to ensure accuracy with the architectural plan.

c. Team Coordination & Plan Review:

  • Multiple discussions were held between the architect, engineer, and construction team to clarify technical details.

  • Structural plan sheets were referred to and marked on-site for execution alignment.

  • A team review session was conducted to ensure all team members understood the next phase of execution.


3. Instructions / Recommendations Given:

  • Ensure consistent curing for structural concrete members, especially the staircase and slab.

  • Maintain uniformity in column and beam shuttering with proper vertical alignment.

  • Strictly follow the given architectural and structural drawings to avoid any design discrepancies.

  • Improve site cleanliness and material stacking to enhance safety and accessibility.


4. Team Interaction Summary:

  • The site team was briefed and guided regarding upcoming construction stages.

  • Site engineers and workers were cooperative and responsive to suggestions and corrections.

  • A group photo was taken to document the visit and collaboration.


5. Overall Assessment:

The project is progressing steadily with satisfactory quality control. With continued adherence to the provided plans and construction best practices, the project is expected to proceed smoothly.


Prepared By:
Dr. Chandra Shekhar Changeriya
Architect | Indian Architect Team

Reviewed By:
Er. Arjun Janva
Engineer | Indian Architect Team